Solar power station,


Tokmak city

Power:

50MW

Location:

Zaporizhya Region

Area:

96Ha

ABOUT THE PROJECT

In the second quarter of 2018, the construction of the first stage of 25 MW was completed. At the moment, the construction of the second stage with a capacity of 25 MW is being implemented.

Date of completion of the project 50 MW: November 2018

Within the project it is constructed:

  • Own increasing substation 10/150 kV;
  • Administrative and household complex 432 m2;
  • The transmission line is 150 kV (4 km) connecting the solar power plant «Tokmak Solar Energy» with the power transmission line No. 112 of PJSC «Zaporozhyeoblenergo»